When qualifying a welding procedure specification (WPS) under ASME Section IX, changing the base metal P-Number typically requires:
-
A
Updating the WPS document only
-
B
Requalification of the procedure with a new PQR
-
C
Notifying the owner in writing
-
D
Increasing the preheat temperature by 50ยฐF