Pipefitter Pipe Fabrication Methods 4 — Questions and Answers
Question 1: What is the minimum preheat requirement purpose when welding on high-carbon or alloy steel pipe during fabrication?
- To speed up welding travel speed
- To reduce the risk of hydrogen-induced cracking in the heat-affected zone (Correct answer)
- To increase the weld bead width
- To eliminate the need for post-weld heat treatment
Correct answer: To reduce the risk of hydrogen-induced cracking in the heat-affected zone
Preheat slows the cooling rate of the weld and HAZ, reducing the risk of hydrogen-induced (cold) cracking in hardenable steel alloys.
Question 2: In shop fabrication, what is the primary advantage of using a pipe positioner (turning roll) during welding?
- It eliminates the need for filler metal
- It keeps the weld in the flat (1G) position throughout the joint (Correct answer)
- It preheats the base metal automatically
- It measures wall thickness during welding
Correct answer: It keeps the weld in the flat (1G) position throughout the joint
A pipe positioner rotates the pipe so the welder can maintain the flat 1G position, producing higher-quality, faster welds.
Question 3: Which pipe end preparation is required for a standard butt weld joint on pipe with wall thickness greater than 3/16 inch?
- Plain square cut end
- Beveled end at approximately 37.5 degrees (Correct answer)
- Threaded end with sealant
- Socket end with 0.062-inch shoulder
Correct answer: Beveled end at approximately 37.5 degrees
ASME B31 codes require pipe ends thicker than 3/16 inch to be beveled at approximately 37.5 degrees to allow full penetration groove welds.
Question 4: What is a 'spool' in the context of pipe fabrication?
- A reel used to store welding wire
- A pre-fabricated pipe assembly consisting of pipe, fittings, and flanges ready for field installation (Correct answer)
- A type of pipe hanger support
- A threaded pipe connector
Correct answer: A pre-fabricated pipe assembly consisting of pipe, fittings, and flanges ready for field installation
A spool is a shop-fabricated pipe assembly — a sub-section of piping complete with fittings and flanges — transported to the field for installation.
Question 5: When using an oxy-fuel torch to cut pipe for fabrication, what is the function of the cutting oxygen lever?
- It controls the preheat flame temperature
- It releases a high-pressure stream of oxygen that oxidizes and blows away the molten metal (Correct answer)
- It adjusts the fuel gas flow rate
- It ignites the torch tip
Correct answer: It releases a high-pressure stream of oxygen that oxidizes and blows away the molten metal
The cutting oxygen lever opens a valve that directs a high-pressure oxygen stream onto the preheated metal, causing rapid oxidation and blowing the slag away.
Question 6: Which type of pipe flange is typically used as a companion flange on equipment nozzles and allows for slight angular misalignment during assembly?
- Weld neck flange
- Lap joint flange with stub end (Correct answer)
- Slip-on flange
- Blind flange
Correct answer: Lap joint flange with stub end
A lap joint flange pairs with a stub end and can rotate freely around it, allowing bolt holes to be aligned and accommodating minor angular misalignment.
Question 7: What does 'center-to-center' (C-C) dimension mean on a piping isometric drawing?
- The outer diameter of the pipe
- The distance measured from the center of one fitting or component to the center of another (Correct answer)
- The wall thickness of the pipe
- The gap between two pipe flanges
Correct answer: The distance measured from the center of one fitting or component to the center of another
Center-to-center is the dimension from the centerline intersection of one fitting to the centerline intersection of another, used to lay out piping runs.
What is the minimum preheat requirement purpose when welding on high-carbon or alloy steel pipe during fabrication?