Pipefitter Core Responsibilities 5 — Questions and Answers
Question 1: When installing a pump suction line, the preferred configuration to prevent cavitation is:
- Long, straight horizontal run with an eccentric reducer flat-side up (Correct answer)
- Short vertical drop directly into the pump flange
- Concentric reducer at the pump nozzle to center the flow
- Multiple 90-degree elbows close to the pump inlet
Correct answer: Long, straight horizontal run with an eccentric reducer flat-side up
An eccentric reducer installed flat-side up prevents air pockets from collecting at the pump suction and reduces cavitation risk.
Question 2: Which type of valve is BEST suited for throttling flow control in a process line?
- Gate valve
- Globe valve (Correct answer)
- Ball valve
- Butterfly valve
Correct answer: Globe valve
Globe valves are designed for throttling because their disc moves perpendicular to flow, providing good control over partial openings.
Question 3: A pipefitter notices that a gasket is compressed beyond its recommended torque spec. What is the most likely consequence?
- Improved sealing performance due to higher compression
- Gasket blowout or extrusion leading to leakage (Correct answer)
- Reduced flange face corrosion
- Better alignment of the bolt holes
Correct answer: Gasket blowout or extrusion leading to leakage
Over-torquing a gasket causes it to crush, crack, or extrude beyond the flange face, resulting in leakage.
Question 4: What is the correct sequence for bolt tightening on a pipe flange connection?
- Start at one bolt and tighten in a clockwise circle
- Tighten opposite bolts in a cross or star pattern (Correct answer)
- Tighten the bottom bolts first, then work upward
- Tighten all bolts to half torque simultaneously with an impact gun
Correct answer: Tighten opposite bolts in a cross or star pattern
Cross-pattern tightening ensures even gasket compression and prevents flange cocking or uneven seating.
Question 5: A pipefitter must select the correct pipe hanger spacing for a 4-inch schedule 40 carbon steel line carrying water. The primary factor governing maximum span is:
- The insulation thickness on the pipe
- The allowable sag and stress in the pipe between supports (Correct answer)
- The height of the pipe above the floor
- The ambient temperature of the installation area
Correct answer: The allowable sag and stress in the pipe between supports
Hanger spacing is determined by allowable pipe deflection and bending stress, as specified in MSS SP-69 or ASME B31 codes.
Question 6: Which of the following is a pipefitter's responsibility when reviewing an isometric drawing before fabrication?
- Approving the drawing for engineering sign-off
- Verifying dimensions, material specs, and weld symbols match the design intent (Correct answer)
- Ordering all listed materials without further review
- Signing off on the hydrostatic test results
Correct answer: Verifying dimensions, material specs, and weld symbols match the design intent
Before fabrication, a pipefitter must confirm that dimensions, material callouts, and weld details on the iso match the piping specification and P&ID.
Question 7: What does PWHT stand for, and why is it performed on certain welds in pressure piping?
- Pre-Weld Heat Treatment — to preheat the base metal before welding
- Post-Weld Heat Treatment — to relieve residual stresses and restore toughness after welding (Correct answer)
- Pressurized Weld Hardness Test — to verify weld hardness after completion
- Pipe Wall Heat Test — to check for internal corrosion after welding
Correct answer: Post-Weld Heat Treatment — to relieve residual stresses and restore toughness after welding
PWHT reduces residual welding stresses and restores ductility, and is required by code for certain materials, wall thicknesses, and services.
When installing a pump suction line, the preferred configuration to prevent cavitation is: