When should a paving inspector require a new Proctor test (reference standard) for subbase material?
-
A
When the source material or borrow pit changes significantly
-
B
Every 500 linear feet of compacted subbase
-
C
After every rainfall event during construction
-
D
Only when the contractor requests it