A change order is issued that alters the scope of a paving contract. The inspector's responsibility regarding documentation is to:
-
A
Ignore the change order until final payment
-
B
Record the change order number, date, and description in the daily diary and adjust quantity tracking accordingly
-
C
Rewrite the original project specifications to match the change
-
D
Notify OSHA of the scope change