A paving inspector notices that silt fences on a project have been installed parallel to the slope contours but are sagging and not trenched in. What corrective action is required?
-
A
Replace silt fences with sediment basins immediately
-
B
Re-install the silt fences with the fabric trenched and backfilled into the ground
-
C
Add additional posts every 10 feet to support the sag
-
D
Remove the silt fences since they are installed incorrectly and are ineffective