According to the PMI Standard for Portfolio Management, what is the primary purpose of portfolio risk management?
-
A
To eliminate all risks associated with portfolio components
-
B
To optimize the portfolio's risk exposure in alignment with organizational risk appetite
-
C
To document all potential threats and assign them to project managers
-
D
To avoid high-risk components and focus only on low-risk initiatives