A budget variance report showing that actual expenditures are significantly less than budgeted amounts most likely indicates:
-
A
The school overspent its allocation in a prior period
-
B
Underspending that could signal unmet program goals or delayed purchases
-
C
The budget was incorrectly calculated at the beginning of the year
-
D
Revenue collections exceeded projections for the reporting period