A licensed electrical contractor discovers mid-project that the permit they pulled was for a different scope of work than what the owner now requests. What is the correct action?
-
A
Proceed with the new scope since a permit is already on file
-
B
Stop work and obtain an amended or new permit before continuing
-
C
Complete the work and note the change in the final inspection report
-
D
Notify OSHA and continue working under the original permit