A contractor receives a change order request that would add $12,000 to the contract. The owner asks the contractor to begin work immediately before signing the change order. What is the most prudent course of action?
-
A
Begin work immediately to maintain good owner relations
-
B
Refuse work until the signed change order is received
-
C
Begin work but document the request in writing to the owner
-
D
Require a verbal agreement from the owner's representative