A project has a budget at completion (BAC) of $150,000. At the current time, the earned value (EV) is $75,000, the planned value (PV) is $80,000, and the actual cost (AC) is $90,000. What is the Cost Performance Index (CPI) for this project?
-
A
1.20
-
B
0.94
-
C
0.83
-
D
1.07