An electrical contractor is setting up a temporary power supply on a construction site. According to OSHA standard 1926.404, what is required for all 120-volt, single-phase, 15- and 20-ampere receptacle outlets on construction sites that are not part of the permanent wiring of the building?
-
A
They must be protected by a weather-resistant cover.
-
B
They must be connected to a circuit with a maximum of two outlets.
-
C
They must have ground-fault circuit-interrupter (GFCI) protection.
-
D
They must be inspected and approved by the general contractor daily.