An electrical contractor is working on a commercial build-out under a lump-sum contract. The owner requests adding 10 additional duplex receptacles that were not in the original plans. What is the first and most appropriate document the contractor should initiate to formally address this change?
-
A
A Request for Information (RFI)
-
B
A Change Order Proposal (COP)
-
C
An invoice for the additional work
-
D
A notice of delay