According to BS 7671, what is the correct sequence of tests for initial verification of an electrical installation?
-
A
Insulation resistance, continuity, polarity, earth fault loop impedance, RCD
-
B
Continuity of protective conductors, continuity of ring final circuits, insulation resistance, polarity, earth fault loop impedance, RCD operation
-
C
RCD operation first, then all other tests in any order
-
D
Earth fault loop impedance, RCD, continuity, insulation resistance