NCARB - National Council of Architectural Registration Boards Practice Test
▶
NCARB Construction and Evaluation 3
Free · Instant Results
During construction, the owner requests a significant design change that increases the contract sum. What document should be used?
A
Change Order
B
Architect's Supplemental Instruction
C
RFI Response
D
Field Order