An inspector observes a contractor using an incorrect abrasive type that is not compliant with the project specification. After verbally notifying the contractor's foreman, what is the inspector's MOST critical next step regarding documentation?
-
A
Note the deviation in a private field book for later reference.
-
B
Wait until the end of the shift to include it in the daily report.
-
C
Issue a formal Non-Conformance Report (NCR) detailing the deviation and required corrective action.
-
D
Request the coating manufacturer's opinion on the alternative abrasive.