A project to build a data center in a coastal area identifies a high risk of project delays due to potential hurricane activity during the planned construction period. The project team decides to purchase and pre-position advanced, weather-resistant building materials and to create a detailed emergency shutdown and startup plan to minimize downtime after a storm. Which risk response strategy is the team employing?