Which statement best describes the primary difference between Preventive Maintenance (PM) and Predictive Maintenance (PdM)?
-
A
PM is performed after a failure, while PdM is performed before.
-
B
PM is based on a fixed schedule, while PdM is based on the actual condition of the equipment.
-
C
PdM uses only visual inspections, while PM uses advanced technology.
-
D
PM is always less expensive than PdM.