A project team is pursuing the MR Credit: Building Product Disclosure and Optimization - Environmental Product Declarations. To meet the requirements for Option 1, what is the minimum number of different permanently installed products with qualifying EPDs that must be sourced from a minimum number of different manufacturers?
-
A
10 products from 3 manufacturers
-
B
15 products from 4 manufacturers
-
C
20 products from 5 manufacturers
-
D
25 products from 5 manufacturers