A manufacturing company uses a planning system to determine the quantity and timing for acquiring dependent demand items, such as raw materials and subassemblies, needed to create its finished goods. The system uses the Master Production Schedule (MPS) as a primary input. Which system is being described?
-
A
Distribution Requirements Planning (DRP)
-
B
Enterprise Resource Planning (ERP)
-
C
Material Requirements Planning (MRP)
-
D
Capacity Requirements Planning (CRP)