In a construction project, what is the scheduler's primary responsibility related to procurement activities?
-
A
Incorporating material and equipment delivery lead times into the project schedule
-
B
Negotiating vendor contracts on behalf of the owner
-
C
Approving purchase orders for subcontractors
-
D
Setting the final budget for procurement packages