A stakeholder requests a feature mid-Sprint that they consider urgent. What should the Product Owner do?
-
A
Add it to the current Sprint immediately
-
B
Add it to the Product Backlog and prioritize it for a future Sprint
-
C
Ask the Development Team to work overtime to include it
-
D
Cancel the current Sprint and start a new one