A stakeholder insists on adding a feature mid-Sprint that conflicts with the current Sprint Goal. What should the Product Owner do?
-
A
Add the feature immediately to satisfy the stakeholder
-
B
Negotiate with the stakeholder and explain the impact on the Sprint Goal
-
C
Ignore the stakeholder until the Sprint ends
-
D
Ask the Scrum Master to reject the request