A Product Owner discovers that two key stakeholders have conflicting requirements for the next Sprint. What is the BEST approach?
-
A
Escalate the conflict to the Scrum Master for resolution
-
B
Prioritize the requirement from the stakeholder with higher authority
-
C
Facilitate a conversation between stakeholders to find a shared understanding and make a transparent prioritization decision
-
D
Implement both requirements partially to satisfy both stakeholders