What is 'capacity requirements planning' (CRP) and when is it performed?
-
A
CRP translates MRP planned and released orders into detailed work center load requirements, performed after MRP
-
B
CRP sets the overall production rate for the S&OP process
-
C
CRP validates the MPS against key resources before MRP is run
-
D
CRP calculates safety stock levels based on demand variability