A facility manager is overseeing a multi-phase office renovation. During the project closeout phase, the primary objective is to finalize all activities. Which of the following tasks is MOST critical to perform during project closeout?
-
A
Conducting a post-occupancy evaluation to assess user satisfaction.
-
B
Archiving project documentation, including as-built drawings and warranties, and ensuring all financial accounts are settled.
-
C
Releasing the project team to their next assignments to optimize resource allocation.
-
D
Initiating the planning process for the next phase of the renovation to maintain project momentum.