Under the EPA's Construction General Permit (CGP), when is a permittee typically required to transition from construction-phase BMPs to post-construction stormwater controls?
-
A
Immediately after final grading is complete
-
B
When the site reaches final stabilization and permit coverage is terminated
-
C
After the first post-construction inspection
-
D
30 days after the last rainfall event exceeding 0.5 inches