A SWPPP must be amended within a specific timeframe after certain events. Which of the following scenarios triggers a mandatory SWPPP amendment under the typical EPA Construction General Permit (CGP)?
-
A
A change in the project's construction schedule that delays the start date by one month.
-
B
A change in design, construction, operation, or maintenance that has a significant effect on the potential for pollutant discharge.
-
C
The replacement of one brand of silt fence with a different brand that has equivalent specifications.
-
D
A routine weekly inspection identifies that a BMP requires minor maintenance.