An inspector observes a rock check dam in a channel with a 4% grade. The crest of the downstream dam is at the same elevation as the toe of the upstream dam. Sediment has accumulated to approximately half the height of the downstream dam. What is the most appropriate action for the inspector to recommend?
-
A
Add another check dam between the existing ones to improve efficiency.
-
B
Remove the accumulated sediment from the upstream side of the dam.
-
C
Reconstruct the dam to be 12 inches lower in the center than at the edges.
-
D
No action is needed as the check dam is functioning as designed.