A Scrum Team consistently fails to complete the work they forecast. During a Sprint Retrospective, the Developers reveal they are often pulled away to work on "urgent" tasks by a department manager, a fact they had not previously shared. This lack of openness is a failure to uphold which pillar of Scrum?
-
A
Inspection
-
B
Adaptation
-
C
Transparency
-
D
Courage