A construction change order is a formal written agreement that modifies the original contract by adjusting:
-
A
Only the project schedule
-
B
Scope, price, and/or schedule as mutually agreed by owner and contractor
-
C
Only the contractor's profit margin
-
D
The subcontractor's bonding requirements