Which project management tool is most commonly used by construction auditors to evaluate schedule performance against planned milestones?
-
A
Earned Value Management (EVM)
-
B
Critical Path Method (CPM) alone
-
C
Resource Leveling Chart
-
D
Gantt Chart without baselines