Under a lump sum construction contract, which condition typically gives a contractor the right to submit a change order request?
-
A
Owner-directed changes to the original project scope
-
B
Contractor's own inefficiency in executing the work
-
C
Increases in the contractor's overhead costs
-
D
Subcontractor defaults on their obligations