An automotive recycling facility with an SPCC Plan installs a new 1,000-gallon aboveground used oil tank, which represents a significant change in its storage configuration. According to EPA regulations, what action is required regarding the SPCC Plan documentation?
-
A
The plan must be completely rewritten by a new Professional Engineer within 30 days.
-
B
The facility must notify the EPA Regional Administrator by certified mail before using the new tank.
-
C
The plan must be amended within six months of the change and the amendment implemented as soon as possible.
-
D
No action is required as long as the total facility storage capacity remains under 10,000 gallons.