What is the primary purpose of the 'Close Project or Phase' process in the PMBOK Guide?
-
A
To reassign team members to new projects
-
B
To formally finalize all activities, transfer deliverables, and close out the project or phase
-
C
To update the risk register with final risk outcomes
-
D
To archive only financial records for audit purposes