How does Agile manage risk differently from traditional project management?
-
A
Agile ignores risk until it becomes an issue
-
B
Agile manages risk through continuous delivery of small increments that reveal risks early
-
C
Agile documents all risks in a register at project start and reviews quarterly
-
D
Agile assigns a dedicated risk manager to each team