A project team for a new weather satellite has successfully integrated all subsystems. They are now conducting a series of tests to ensure the satellite's sensors collect data according to the detailed performance specifications outlined in the system requirements document. Which process is the team primarily engaged in?
-
A
System Validation
-
B
System Integration
-
C
System Verification
-
D
Requirements Analysis