A systems engineering team identifies a potential risk that a key supplier for a custom component might go out of business. After identifying this risk, what is the most critical next step in the risk management process?
-
A
Immediately select an alternate supplier to start fabricating the part.
-
B
Analyze the probability of the supplier failing and the impact on the project's cost and schedule.
-
C
Purchase insurance to cover the potential financial loss.
-
D
Accept the risk and add extra time to the project schedule as a buffer.