A risk manager is using a risk analysis technique that starts with a top-level event (e.g., system failure) and deductively works backward to identify all the potential underlying causes. This technique uses logic gates like 'AND' and 'OR' to model the relationships between events. Which risk analysis technique is being used?
-
A
Event Tree Analysis (ETA)
-
B
Fault Tree Analysis (FTA)
-
C
Bow-Tie Analysis
-
D
SWOT Analysis