OSP Codes Compliance & Project Documentation 2 ā Questions and Answers
Question 1: Which OSHA standard specifically governs excavation and trenching safety for OSP construction crews?
- 29 CFR 1926 Subpart P (Correct answer)
- 29 CFR 1910 Subpart Q
- 29 CFR 1926 Subpart T
- 29 CFR 1910 Subpart J
Correct answer: 29 CFR 1926 Subpart P
OSHA 29 CFR 1926 Subpart P covers excavations and trenching safety requirements for construction work.
Question 2: A redline markup on an as-built drawing indicates:
- A proposed change pending approval
- An actual field deviation from the design drawing (Correct answer)
- A safety hazard requiring immediate correction
- A rejected design option
Correct answer: An actual field deviation from the design drawing
Redline markups on as-built drawings record actual field conditions or deviations that differ from the original design.
Question 3: Under the National Electrical Safety Code (NESC), what is the minimum horizontal clearance between communication cables and power lines of 750V to 22kV on joint-use poles?
- 12 inches
- 24 inches
- 30 inches (Correct answer)
- 40 inches
Correct answer: 30 inches
NESC requires a minimum 30-inch horizontal clearance between communication cables and power lines in the 750Vā22kV range on joint-use structures.
Question 4: A permit-to-work (PTW) document for OSP work primarily serves to:
- Authorize billing for the project
- Control and communicate hazards before work begins (Correct answer)
- Record the final inspection outcome
- Approve subcontractor qualifications
Correct answer: Control and communicate hazards before work begins
A permit-to-work formally identifies hazards, required precautions, and authorizes personnel to perform specific tasks safely.
Question 5: When a project requires work within a railroad right-of-way, which document is typically required before construction begins?
- FAA Flight Clearance
- Railroad Flagging Agreement or Encroachment Permit (Correct answer)
- Corps of Engineers Section 404 Permit
- FCC Experimental License
Correct answer: Railroad Flagging Agreement or Encroachment Permit
Railroads require a flagging agreement or encroachment permit to control worker safety and liability within their right-of-way.
Question 6: In OSP project documentation, a 'make-ready' survey is used to determine:
- The final cable route path selection
- What pole or conduit modifications are needed before attachment (Correct answer)
- Grounding electrode resistance values
- Fiber splice loss budgets
Correct answer: What pole or conduit modifications are needed before attachment
A make-ready survey identifies existing infrastructure conditions and any modifications (such as transfers or pole replacements) required before new facilities can be attached.
Question 7: Which regulation requires notification to a one-call center before excavating, and typically requires a minimum notice period of 2ā3 business days?
- EPA Clean Water Act Section 402
- State underground facility protection laws (dig safe laws) (Correct answer)
- NESC Rule 200
- DOT 49 CFR Part 192
Correct answer: State underground facility protection laws (dig safe laws)
State one-call or 'dig safe' laws require advance notification to locate underground utilities before excavation to prevent damage and injury.
Which OSHA standard specifically governs excavation and trenching safety for OSP construction crews?