OM Project Management Fundamentals 3 — Questions and Answers
Question 1: Which conflict resolution technique is considered most effective in project management because it results in a win-win outcome?
- Smoothing
- Forcing
- Compromising
- Collaborating (Problem Solving) (Correct answer)
Correct answer: Collaborating (Problem Solving)
Collaborating (problem solving) addresses the root cause and finds a solution acceptable to all parties, producing lasting resolution.
Question 2: A Work Breakdown Structure (WBS) decomposes project deliverables into work packages. What rule defines when decomposition is sufficient?
- Each work package takes exactly one week
- Work packages can be reliably estimated and assigned (Correct answer)
- No more than six levels of decomposition exist
- Each package costs less than $10,000
Correct answer: Work packages can be reliably estimated and assigned
Decomposition is complete when work packages can be reliably estimated, scheduled, monitored, and assigned to a responsible party.
Question 3: A project manager is leading a cross-functional team where members still report to their functional managers. Which organizational structure does this describe?
- Projectized
- Functional
- Matrix (Correct answer)
- Composite
Correct answer: Matrix
In a matrix organization, team members report to both the project manager and their functional manager simultaneously.
Question 4: During quality planning, a project manager creates a diagram showing potential causes of a quality defect. Which tool is this?
- Pareto Chart
- Control Chart
- Ishikawa (Fishbone) Diagram (Correct answer)
- Run Chart
Correct answer: Ishikawa (Fishbone) Diagram
The Ishikawa (cause-and-effect or fishbone) diagram maps potential causes organized into categories to identify root causes of defects.
Question 5: Which communication model component represents interference that distorts the message between sender and receiver?
- Encoding
- Medium
- Noise (Correct answer)
- Feedback
Correct answer: Noise
Noise is any interference—physical, psychological, or semantic—that distorts or disrupts the communication between sender and receiver.
Question 6: A project sponsor requests a change that increases project scope after the project baseline has been approved. What process should the project manager initiate?
- Update the project charter
- Implement the change immediately
- Submit an Integrated Change Control request (Correct answer)
- Revise the WBS and proceed
Correct answer: Submit an Integrated Change Control request
All scope changes after baseline approval must go through Integrated Change Control to evaluate impact and obtain formal approval before implementation.
Question 7: In agile project management, what is the primary purpose of a Sprint Retrospective?
- To review deliverables with the customer
- To plan work for the next sprint
- To inspect the process and identify improvements for the team (Correct answer)
- To update the product backlog
Correct answer: To inspect the process and identify improvements for the team
The Sprint Retrospective focuses on the team's process, relationships, and tools to identify improvements for future sprints.
Which conflict resolution technique is considered most effective in project management because it results in a win-win outcome?