OM Financial Management & Budgeting 3 — Questions and Answers
Question 1: Which cost behavior remains constant in total regardless of changes in production volume within the relevant range?
- Variable costs
- Mixed costs
- Fixed costs (Correct answer)
- Step costs
Correct answer: Fixed costs
Fixed costs (e.g., rent, salaries of permanent staff) do not change in total as production volume fluctuates within the relevant range.
Question 2: A nonprofit organization must allocate indirect costs to federal grants. Which federal cost principles document governs this allocation?
- OMB Circular A-133
- 2 CFR Part 200 (Uniform Guidance) (Correct answer)
- FASB ASC 958
- GAAP Codification Topic 840
Correct answer: 2 CFR Part 200 (Uniform Guidance)
2 CFR Part 200 (Uniform Guidance) establishes federal cost principles, audit requirements, and administrative requirements for non-federal entities receiving federal awards.
Question 3: When preparing a cash flow forecast, which item is typically included in operating activities under the indirect method?
- Proceeds from issuing bonds
- Purchase of equipment
- Depreciation added back to net income (Correct answer)
- Payment of dividends
Correct answer: Depreciation added back to net income
Under the indirect method, non-cash charges like depreciation are added back to net income because they reduced income but did not use cash.
Question 4: An activity-based costing (ABC) system differs from traditional costing because it:
- Assigns overhead based solely on direct labor hours
- Uses multiple cost drivers to trace overhead to products or services (Correct answer)
- Ignores indirect costs entirely
- Allocates costs equally across all departments
Correct answer: Uses multiple cost drivers to trace overhead to products or services
ABC identifies multiple cost drivers (e.g., machine setups, purchase orders) to allocate overhead more accurately than single-rate methods.
Question 5: A manager reviewing the budget sees 'favorable variance' on a line item. This MOST likely means:
- Actual costs exceeded budgeted costs
- Actual revenue fell below budgeted revenue
- Actual costs were lower than budgeted costs (Correct answer)
- The budget was not approved on time
Correct answer: Actual costs were lower than budgeted costs
A favorable cost variance occurs when actual spending is less than the budgeted amount, improving the financial position.
Question 6: Which financial metric measures how efficiently an organization collects its receivables?
- Debt-to-equity ratio
- Days sales outstanding (DSO) (Correct answer)
- Gross profit margin
- Operating leverage
Correct answer: Days sales outstanding (DSO)
DSO (also called accounts receivable days) measures the average number of days it takes to collect payment after a sale is made.
Question 7: A top-down budget approach means that:
- Front-line employees submit budget requests that are approved upward
- Senior leadership sets overall spending targets that cascade down to departments (Correct answer)
- Each unit competes for resources in an open bidding process
- Budgets are built from historical cost data without adjustment
Correct answer: Senior leadership sets overall spending targets that cascade down to departments
Top-down budgeting starts with executive-level targets and directives that are then distributed to lower organizational levels for implementation.
Which cost behavior remains constant in total regardless of changes in production volume within the relevant range?