Nutanix Exam Project Planning & Execution 3 — Questions and Answers
Question 1: When planning a Nutanix AHV migration from VMware, which activity should appear earliest in the project schedule?
- Migrating production VMs
- Conducting a workload inventory and compatibility assessment (Correct answer)
- Decommissioning VMware hosts
- Training end users
Correct answer: Conducting a workload inventory and compatibility assessment
A workload inventory and compatibility assessment must precede migration to identify unsupported features and plan remediation.
Question 2: A project sponsor requests weekly status reports for a Nutanix infrastructure rollout. Which information is most essential to include?
- Detailed server hardware specifications
- Schedule variance, budget status, and top risks (Correct answer)
- Full change log of every configuration setting
- Employee timesheets
Correct answer: Schedule variance, budget status, and top risks
Executive status reports should focus on schedule variance, budget health, and top risks to enable informed decision-making.
Question 3: A Nutanix cluster expansion project is delayed because hardware shipment is two weeks late. This is an example of which type of project constraint?
- Scope constraint
- External dependency constraint (Correct answer)
- Resource skill gap
- Regulatory compliance constraint
Correct answer: External dependency constraint
Hardware delivery depends on an external vendor, making it an external dependency that can affect project schedule.
Question 4: During Nutanix cluster deployment execution, the team discovers the rack power capacity is insufficient. This issue was not in the risk register. What should the project manager do?
- Halt the project permanently
- Log it as an issue, assess impact, and initiate a change request if scope or cost is affected (Correct answer)
- Ignore it and continue deployment
- Remove it from scope without informing stakeholders
Correct answer: Log it as an issue, assess impact, and initiate a change request if scope or cost is affected
Unplanned issues should be logged, assessed for impact, and escalated through change control if they affect baselines.
Question 5: Which Nutanix Calm feature directly supports project execution by automating repeatable infrastructure provisioning tasks?
- Blueprints (Correct answer)
- Prism Central dashboards
- Flow microsegmentation policies
- Leap disaster recovery plans
Correct answer: Blueprints
Calm Blueprints define application topology and lifecycle actions, enabling consistent and automated infrastructure provisioning.
Question 6: A project manager needs to compress a Nutanix deployment schedule without adding resources. Which technique should be used?
- Fast-tracking non-dependent tasks in parallel (Correct answer)
- Crashing by adding more engineers
- Reducing project scope
- Extending the deadline
Correct answer: Fast-tracking non-dependent tasks in parallel
Fast-tracking overlaps tasks that were originally planned sequentially, compressing the schedule without additional cost.
Question 7: After completing a Nutanix cluster installation, the project team holds a retrospective. What is the primary output of this meeting?
- Updated risk register
- Lessons learned documentation for future projects (Correct answer)
- Final invoice to the client
- Network configuration backup
Correct answer: Lessons learned documentation for future projects
Retrospectives capture lessons learned—what went well and what to improve—to benefit future projects.