An engineer serving as the owner's representative observes that a contractor is falling behind schedule. What is the most appropriate initial action?
-
A
Terminate the contractor immediately
-
B
Notify the owner and issue a written notice to the contractor requesting a recovery schedule
-
C
Ignore the delay and reassess at the next milestone
-
D
Direct the contractor's workers to work overtime without authorization