During the construction phase of a project, the owner requests a change that will significantly increase the project scope. What is the engineer's FIRST obligation?
-
A
Implement the change immediately to maintain client satisfaction
-
B
Issue a formal change order and assess impacts on schedule and budget before proceeding
-
C
Refuse the change because the contract is already signed
-
D
Consult only with the contractor about feasibility