A design firm completes 80% of its contracted services before the client wrongfully terminates the agreement. The firm's best contractual remedy is to claim:
-
A
Only the value of work completed under quantum meruit
-
B
Expectation damages including anticipated profit on the unperformed portion
-
C
Reliance damages limited to out-of-pocket costs incurred
-
D
Restitution of all fees paid by the client