An architect discovers that a subcontractor's bid was based on a clerical error that significantly understated the cost. Under contract law, the subcontractor may seek relief under the doctrine of:
-
A
Promissory estoppel
-
B
Unilateral mistake
-
C
Mutual mistake
-
D
Fraudulent misrepresentation