In a qualitative risk assessment for an engineering project, risks are typically evaluated based on which two dimensions?
-
A
Budget and schedule
-
B
Probability of occurrence and severity of impact
-
C
Stakeholder concern and media coverage
-
D
Design complexity and construction difficulty