What is the primary advantage of using a unit price contract versus a lump sum contract for an electrical contractor?
-
A
The contractor bears all risk for quantity variations
-
B
Payment is tied to actual quantities installed, reducing quantity risk
-
C
The owner takes on all responsibility for scheduling
-
D
Labor rates are fixed regardless of market conditions