In a Critical Path Method (CPM) project schedule, the critical path is defined as:
-
A
The shortest path through the project network
-
B
The longest path through the project network, which controls the project duration
-
C
The path containing activities with the greatest resource demands
-
D
The path with the most probabilistic duration uncertainty